This release includes the current first-pass source ledger. Open any source to inspect the original material. The underlying research database is maintained as a working source record and may change as corrections are verified.
SRC-0001DC-CA-0001
Meta · Company announcement · Primary
AI campus announcement, reported scale and cooling claims
Company statement; project performance claims are forward-lookingSRC-0002DC-CA-0002
Government of Alberta · Government project listing · Primary
Proposed AI hub and reported generation capacity
Government listing; confirm exact site and current approvalsSRC-0003DC-CA-0003
Government of Alberta · Government project listing · Primary
Proposed AI hub, location region and stated 960 MWe capability
Government warns map pin is not preciseSRC-0004DC-CA-0004
Town of Olds · Municipal announcement · Primary
Proposed AI/cloud data-centre project and proponent claims
Town announcement; grid/power status needs regulatory verificationSRC-0005DC-CA-0005
Gryphon Digital Mining · SEC filing · Primary
Pincher Creek asset intended for HPC/AI infrastructure
Forward-looking company disclosure; construction status unverifiedSRC-0006DC-CA-0006
Bitdeer · Company announcement · Primary
Groundbreaking, 101 MW generation/100 MW computing capacity and future HPC/AI flexibility
AI workload is future flexibility, not confirmed initial useSRC-0007DC-CA-0007
TELUS · Company announcement · Primary
Kamloops AI Factory, planned online later in 2026
Cluster-wide water and power figures are not site-specificSRC-0008DC-CA-0008
TELUS · Company announcement · Primary
M3 AI Factory in Mount Pleasant, Vancouver; planned end-2026 opening
Cluster-wide water and power figures are not site-specificSRC-0009DC-CA-0009
TELUS · Company announcement · Primary
150 West Georgia AI Factory target online 2029
Cluster-wide water and power figures are not site-specificSRC-0010DC-CA-0010
Bell Canada · Company announcement · Primary
Six-facility B.C. AI-compute supercluster; sites not individually identified
Keep as cluster until sites are publicly disaggregatedSRC-0011DC-CA-0011
Bell Canada · Company announcement · Primary
300 MW purpose-built AI data-centre development near Regina
Timeline is forecast; construction milestone needs confirmationSRC-0012DC-CA-0012
HIVE / BUZZ HPC · Company announcement · Primary
Planned 320 MW GTA AI project; exact municipality undisclosed
Forward-looking; land, delivery and final siting need verificationSRC-0013DC-CA-0013
Accelsius · Company announcement · Primary
Planned 300 MW Ontario AI campus; exact location undisclosed
Vendor announcement; permitting/land status not establishedSRC-0014DC-CA-0014
NorthVault AI · Company announcement · Primary
Staged AI campus capacity and conditional energization timeline
Company says final delivery remains conditionalSRC-0015DC-CA-0015
HIVE Digital Technologies · SEC filing · Primary
Acquired Toronto/GTA facility for sovereign AI/HPC expansion
Street location and operational GPU count undisclosedSRC-0016DC-CA-0016
CBC News · News reporting · Secondary
Withdrawn AI proposal and reported scope/water claim
Independent reporting; developer claims attributedSRC-0017DC-CA-0017
QScale · Company announcement · Primary
Lévis Building B construction and 60 MW IT capacity
Waste-heat plan is not confirmed operating recoverySRC-0018DC-CA-0018
La Caisse · Investor announcement · Primary
Montréal MTL8 operating 21 MW AI-ready facility
Capacity type not restated as IT or utility loadSRC-0019DC-CA-0019
Beacon Data Centers / VoltaGrid · Project website · Primary
Proposed Saint John AI hub, up-to-400 MW design and cooling claims
EIA and grid evidence needed before treating project claims as approvalsSRC-0020Methodology / policy
Government of Alberta · Government policy · Primary
Dedicated-generation/storage approach and AESO allocation context
Current policy page; confirm project-specific allocation separatelySRC-0021Methodology / policy
IESO · Grid operator guidance · Primary
Technical requirements for large computational loads
Does not constitute project approvalSRC-0022Methodology / policy
BC Hydro · Utility program · Primary
AI/data-centre demand allocation program
Application/feasibility is not final allocationSRC-0023Methodology / policy
Innovation, Science and Economic Development Canada · Government program · Primary
Federal >100 MW intake; does not name selections or approvals
Do not imply applicants are selected, funded or approvedSRC-0024DC-CA-0001
Sturgeon County · Municipal planning / permits · Primary
Master-site milestones and May 2026 grading permit for site preparation; construction expected Q3/Q4 2026; operations target 2029
Municipal page; avoid reproducing street address and do not treat as operating statusSRC-0025DC-CA-0003
Alberta Utilities Commission · Regulator application · Primary
920 MW thermal power plant application under review to supply co-located data halls
Application/hearing is not an approvalSRC-0026DC-CA-0004
Alberta Utilities Commission · Regulator decision · Primary
AUC denied associated 1,400 MW gas plant / 1,800 MW emergency-diesel application
Decision concerns power project; does not by itself permanently cancel every possible data-centre conceptSRC-0027DC-CA-0004
Town of Olds · Municipal status page · Primary
Town reports no active development permit application for proposed Olds data-centre projects
Current municipal status; does not establish future outcomeSRC-0028DC-CA-0005
Gryphon Digital Mining / SEC · SEC issuer disclosure · Primary
Reports May 2025 assignment of Gryphon rights/interests related to the Captus site
Current developer/ownership remains unverified without newer recordsSRC-0029DC-CA-0009
City of Vancouver · Municipal planning decision · Primary
Council approved amendment allowing Bulk Data Storage use
Predates TELUS announcement; not a TELUS construction, power-service or operating approvalSRC-0030DC-CA-0011
Impact Assessment Agency of Canada · Federal assessment registry decision · Primary
Registry says physical activity had substantially begun; describes proposed 300 MW AI data centre in RM of Sherwood
Not an environmental approval or effects findingSRC-0031DC-CA-0012
Town of Oakville · Municipal planning status · Primary
Town had not received a data-centre development application and passed interim control by-law
Does not locate or identify the BUZZ/HIVE GTA proposalSRC-0032DC-CA-0016
Township of Armour · Council minutes · Primary
Conditional support-in-principle only; council requested Hydro One capacity, water/septic, noise and other details
Not a land sale, permit, capacity confirmation or construction approvalSRC-0033DC-CA-0016
CBC News · News report · Secondary
Reports developer withdrew 2 MW Armour Township proposal
Use pending direct withdrawal letter/council receipt; proponent website appears staleSRC-0034DC-CA-0017
QScale · Company construction announcement · Primary
QScale says Q01 Building B construction is well underway and will add 60 MW IT capacity
Operator-reported construction; municipal and grid approvals not independently locatedSRC-0035DC-CA-0018
Cologix · Company status announcement · Primary
Cologix says 21 MW MTL8 facility is in service at Technoparc Montréal
Operator statement; no municipal occupancy record locatedSRC-0036DC-CA-0019
Government of New Brunswick · Provincial EIA registry · Primary
Spruce Lake AI Data Centre Project: Beacon New Brunswick Inc. and VoltaGrid LLC; 390 MW; determination review in progress
Registration/review is not a certificate, grid award, construction authorization or operating approvalSRC-0037DC-CA-0019
Stantec for Beacon New Brunswick Inc. and VoltaGrid LLC · Filed EIA registration · Primary project filing
Filed proposal: 390 MW = 190 MW on-site gas + 200 MW proposed NB Power supply; proposed closed-loop cooling initial fill about 3,500 m3
Proponent/consultant filing, not a regulator determination; permits still prospectiveSRC-0038DC-CA-0001
Sturgeon County · Municipal acknowledgement · Primary
County acknowledgement names Treaty 6 territory, Alexander and Michel First Nations, and Métis Nation of Alberta Districts 8 and 11
Municipal acknowledgement only; not a project-specific territory, title, rights-holder, consultation or consent determinationSRC-0039DC-CA-0007
City of Kamloops · Municipal acknowledgement · Primary
City states it is located on Tk̓emlúps te Secwépemc territory within unceded ancestral lands of the Secwépemc Nation
Municipal acknowledgement only; not project-specificSRC-0040DC-CA-0008
City of Vancouver · Municipal acknowledgement · Primary
City acknowledgement names xʷməθkʷəy̓əm, Sḵwx̱wú7mesh Úxwumixw and səlilwətaɬ Nations
Municipal acknowledgement only; not a project-specific determinationSRC-0041DC-CA-0015
City of Toronto · Municipal acknowledgement · Primary
City describes Toronto as traditional territory of many nations and says it is covered by Treaty 13 and Williams Treaties
City-wide acknowledgement; Toronto/GTA project location is not precise enough to assign a Nation to projectSRC-0042DC-CA-0018
Ville de Montréal · Municipal historical context · Primary
City historical source recognizes millennial First Nations presence on the Island of Montréal
Historical city context only; identifies no project-area rights-holder or territorial findingSRC-0043DC-CA-0019
City of Saint John · Municipal acknowledgement · Primary
City says Saint John/Menaquesk is situated on Wolastoqiyik/Maliseet traditional territory
City-wide acknowledgement only; not an exact Lorneville overlay or project-specific rights/consultation findingSRC-0044DC-CA-0004
CBC News | Journalism | Secondary
Reports AUC refusal and local concerns related to Synapse associated power application
Journalism; refusal applies to the application, not necessarily permanent end of broader conceptSRC-0045DC-CA-0016
BayToday.ca / Local Journalism Initiative | Journalism | Secondary
Reports developer decision not to proceed and municipal study conditions
Small proposal; petition metric is advocacy context, not measure of all local opinionSRC-0046DC-CA-0019
CBC News | Journalism | Secondary
Reports EIA filing details on 390 MW, proposed water system and emissions estimates
Headline/proponent framing; figures are filing estimates subject to review and project changeSRC-0047DC-CA-0011
CBC News | Journalism | Secondary
Reports on RM of Sherwood planning and rezoning materials
Early planning record; not a complete environmental or social impact findingSRC-0048Learning
International Energy Agency | Intergovernmental analysis | Primary technical analysis
Global context on AI, electricity demand, grid bottlenecks and uncertainty
Global modelling, not a measurement or forecast for any Canadian projectSRC-0049Learning
Lawrence Berkeley National Laboratory | Technical report | Primary technical analysis
Definitions for PUE, site and source WUE, and energy-water trade-offs
U.S.-only report; PUE/WUE are not complete environmental impact measuresSRC-0050Learning
North American Electric Reliability Corporation | Reliability assessment | Primary technical analysis
Regional context for large-load forecasts, connections and resource adequacy
North American planning context, not provincial permitting or project approvalSRC-0051Learning
U.S. Department of Energy FEMP | Technical explainer | Primary technical guidance
Plain-language cooling-system and WUE explainer
Federal U.S. guidance, not a benchmark for Canadian facilitiesSRC-0052Learning
LBNL researchers / Resources, Conservation and Recycling | Peer-reviewed research | Peer-reviewed
Explains why workload water use varies by cooling, grid, climate and operations
Not an audited Canadian facility dataset or project-specific water estimate